Weekly Client Status Update Template for Agencies

A weekly client status update should answer three questions in under two minutes of reading: what got done, what's coming next, and is anything at risk. Send it on the same day every week, whether or not there's big news. Clients stop chasing you when they know the update is coming.

When I run delivery for an agency, every client gets a launch update every Friday. It's one of the simplest things I do, and it removes more stress than almost anything else.

Why weekly updates work

When clients don't hear from you, they assume something is wrong. Then they email, or ask for a call, or message the founder directly. A predictable update replaces all of that with one short message they can read on their phone.

It also protects you. If a deadline is at risk because the client hasn't sent feedback, the update puts it in writing early, before it becomes a problem.

The template

Subject: [Client name] weekly update, [date]

Hi [name],

Here's where things stand this week.

Done this week - [Deliverable or milestone, with link] - [Deliverable or milestone, with link]

Coming next week - [What we're working on, with expected date] - [What we're working on, with expected date]

Waiting on you - [What you need, and by when] (or "Nothing this week")

Risks - [Anything that could affect a date, and what we're doing about it] (or "None. Everything is on track for [launch date].")

Key dates - [Next review date] - [Launch date]

Any questions, just reply here.

[Your name]

An example

Subject: Bright Co weekly update, Nov 14

Hi Jordan,

Done this week - Landing page design approved (link) - Three email drafts ready for your review (link)

Coming next week - Landing page build, ready for review Wed Nov 19 - Ad creative, first round Thu Nov 20

Waiting on you - Feedback on the three emails by Tue Nov 18 at noon

Risks - If email feedback comes after Tuesday, the cart open email moves from Dec 1 to Dec 3.

Key dates - Launch: Mon Dec 1

Tips that make it work

Same day, same time, every week. Consistency is the whole point. Friday afternoon works well because it wraps up the week.

Lead with "waiting on you" if it's urgent. Don't bury the thing you need from them.

Be honest about risk. A risk flagged early is a conversation. A risk revealed on launch week is a crisis.

Link, don't attach. Link to the file or task so they always see the latest version.

Keep it short. If it takes more than two minutes to read, cut it.

Where the information comes from

Writing this update should take ten minutes, not an hour. If it takes an hour, your status lives in people's heads instead of your tool. When your project management tool is set up properly, with status, owners, dates and a risk field on every task, the update is mostly copying from one view.

That's one of the clearest signs a team needs better systems. See 10 signs your agency needs an operations manager.

Internal updates too

Send a version of this internally as well. Your founder or leadership team wants the same three answers across every client: what shipped, what's at risk, what's next. Every retainer I run includes this weekly report.

If you'd like updates like this to go out every week without you writing them, that's part of my project management service.